The key to developing this course is working in the best interest of the City to create programs that the city can use to involve the community.
This course is a gem when you look at the acreage and the possibility of the adjacent land help by the airport authority.
My plan would include the distribution of existing baskets to this park while reinforcing our existing parks with new baskets.
Phase 1: We are currently moving forward with this plan; we currently have 27 holes laid out at this location with 3 separate pin locations. Phase 1 is where we evaluate the existing holes, note the areas where there are great pin locations, holes, and conversely identify the areas where the opposite occurs. We plan to leave the current configuration for the upcoming fundraiser on March 6. Currently we have raised 45 dollars with temp basket tourneys held on weekends.
Phase 2: After March 6 we will reverse the configuration still following the contour of the streets, evaluate, and mark the great locations, holes and begin to look for key tee pad areas. This will continue until April, when we will most probably hold another fundraiser that will highlight this design. For anyone interested in getting involved, please contact Tim Finan, who has taken on the responsibility and has stepped up to volunteer and lead this effort.
Phase 3: After Phase 2, we should have a good idea on how to construct this course, which will most probably utilize ideas from Phase 1 and 2. In addition, we will most probably flip the final design 90 degrees. Utilizing the roads more creatively to create a championship caliber course, a driving range and a pitch and putt practice area. It is my hope that will endear us to not only the city of Bridgeton, but also to the Airport Authority who holds land that we hope to be able to utilize in the future.
At this time, however, we need to all be on the same page, I just want to let the members know where I am coming from and what I think we can accomplish in the next 6-8 months.